Release Planning for Samba 3.2

From SambaWiki

3.2.0

(Updated 02-July-2008) The following time based release schedule is currently in play for Samba 3.2.0:

  • Friday, February 29 - Feature freeze for Samba 3.2.0pre2 in the v3-2-stable git branch.
  • Tuesday, March 4 - Samba 3.2.0pre2 has been released.
  • Friday, March 28 - Planned release date for 3.2.0pre3: postponed due to some critical bugs.
  • Friday, April 18 - Planned release date for 3.2.0.: postponed
  • Tuesday, April 22 - Feature freeze for Samba 3.2.0pre3 in the v3-2-stable git branch.
  • Friday, April 25 - Samba 3.2.0pre3 has been released.
  • Friday, May 23 - Samba 3.2.0rc1 has been released.
  • Tuesday, June 10 - Samba 3.2.0rc2 has been released.
  • Tuesday, July 1 - 3.2.0 final has been released.

ToDos (for 3.2.1):